6 + 7 = 13

10-09-2017 - 19:47

Or the largest Artcic SuperStore installation to date

A 2016 installed 150m2 Arctic SuperStore was transforned into a 325m2 cold store in just 22½ hours. 7 additional modules were delivered to the site in west of Ireland during the course of the afternoon/evening.

As the original cold store is in constant use the extension required detailed customer coordination and a super fast installation and completion. This included both of TITAN's HIABS as well as third party haulage. One of TITAN's fork lift trucks was also on site.

This SuperStore is now the largest of TITAN's many SuperStore installations around the world. The previous record holders were in Denmark, UK and Somalia.  

<